Does anyone know if it is possible to skip weekend days when adding an appointment in the scheduler control? I know it is possible to define working hours for a day.
What I need to create is a user drags in an appointment for 56 hours (example). Based on 8 working hours per day the appointment would be devided over 7 days. But then I want to exclude the weekend days. So entering this appointment on a Monday, the last day would be next week Tuesday.
Of course I can split the scheduled appointment into multiple to prevent it being on a weekend but then when the user wants to move it, he has to move multiple appointments. Or I need to program the connection between the appointments and recalculate all when user changes the appointment. I prefer a more simple method like working hours.
Cheers,
Adri |
| |
| |
| | | |
|
| | |
| |
| Publicado el 18,enero 2016 - 15:51 |
Hi Adri,
We ditched the scheduler control for doing that. We simply use the Gant Control. You can define working days and working hours per ressources.
Best regards, Alexandre Leclerc |
| |
| |
| | | |
|
| | |
| |
| Publicado el 18,enero 2016 - 21:58 |
Thanks Alexandre, I will have a look at that.
Cheers, Adri |
| |
| |
| | | |
|
| | | | |
| | |
|