Doubt about the Gantt
Iniciado por CONREISIS, 02,nov. 2020 07:53 - 1 respuesta
Miembro registrado
3 mensajes
Publicado el 02,noviembre 2020 - 07:53
Good nigth, when you join 2 tasks, the slack between them is eliminated (they are tasks followed by one another, there are no days between them).

Do you know how you can add a 2 day slack as shown in the example?





Thank you very much in advance.
Miembro registrado
10 mensajes
Publicado el 03,noviembre 2020 - 09:24
Hi

When you calculate the parents, you could always include a "Start Slack Time" in the task, and then adjust the current task start based of the parent End date + start slack time for this task.

The same principal can be used for parent tasks that might have end slack times attached to them