| Iniciado por CONREISIS, 02,nov. 2020 07:53 - 1 respuesta |
| |
| | | |
|
| |
Miembro registrado 3 mensajes |
|
| Publicado el 02,noviembre 2020 - 07:53 |
Good nigth, when you join 2 tasks, the slack between them is eliminated (they are tasks followed by one another, there are no days between them).
Do you know how you can add a 2 day slack as shown in the example?

Thank you very much in advance. |
| |
| |
| | | |
|
| | |
| |
Miembro registrado 10 mensajes |
|
| Publicado el 03,noviembre 2020 - 09:24 |
Hi
When you calculate the parents, you could always include a "Start Slack Time" in the task, and then adjust the current task start based of the parent End date + start slack time for this task.
The same principal can be used for parent tasks that might have end slack times attached to them |
| |
| |
| | | |
|
| | | | |
| | |
|